AUTOCENTER IN KIEV

STABILIZATION OF THE FOUNDATION
Category
Commercial building
FOCUS
Foundation
LOCATION
Kiev, Ukraine
DATE/YEAR
2016
TECHNOLOGY
Deep Injection

The building of the car center in the Obolonsky district of Kiev.

The reason for petition
Precipitation columns of the building frame, cracks in the walls and partitions.

Problem
Inhomogeneous bulk soil at the base of the foundations.
Sediment of strip foundations of the frame.

Work done
Soil stabilization at the base of the strip foundations of the frame.

Applicable Methods
Deep Injection.

Scope of work
36.5 m.p. (95 sq. m.) Strip foundations.

The work was performed without stopping the operation of the building.

If you didn’t find an object or a situation similar to yours in the portfolio on the website, then order a specialist to select a project to analyze the pros and cons of technologies from the extensive database of completed Uretek projects.
Back to projects
Leave a comment or ask a question
Standard projects and cost
Leave a comment
Comments
Задай вопрос эксперту Uretek

Присылайте нам ваши вопросы и мы ответим на страницах нашего ТехноБлога

Address:
Kiev, Berkovetskaya St., 10
Thanks for your comment!
To close

Leave your phone
and our consultant will contact you

Choose a convenient time to call
  • Services
  • Technologies
  • Portfolio
  • Technoblog
  • About us
  • Contacts
  • +8 800 33 65 15
    Uretek